Today, I’ll be sharing the costs involved in putting up a superstructure of a 4 Bedroom apartment. This estimates consist of the starting process of the block laying till the roofing course.

The project is a 7 bed room house in which the top floor consist of 2 separate 2 bedroom apartment which will be going out for rent. So this estimate talks about the 4 bedroom apartment superstructure work from the block work setup till the roofing course.

Please kindly note that this estimate has been divided into two phases:

Phase 1: which is the Setup to Lintel Stage

Phase 2: which is the Lintel Stage to Roofing Course

 

PHASE 1 : SETUP TO LENTIL STAGE (ESTIMATES) – MAY 2024

  • 5” Hollow : 1,700 PCS X6.5 : 11,050 GHS
  • Cement (32.5r): 20 Bags X72 : 1,440 GHS
  • Cement (Gacem 42.5r) : (20) X97&80 : 1,685 GHS
  • Miscellaneous : 730 GHS
  • Continual Pillars : 14MM (24) X82: 1,968 GHS
  • 3/8 : 10PCS X16 : 160
  • Binding Wire 1 : 70
  • Steel Bender Workmanship: 900
  • Wood for Lentil + T&T (25)X85: 2,350
  • Carpenter Labor(Pillars + Lentil): 1,400
  • Nails : 450 GHS
  • Mason + Laborer Block Laying : 3,260
  • Mason + Laborer Concrete : 1,350
  • Other T&T : 200
  • TOTAL : 27,025 GHS

 

PHASE 2 : LENTIL TO ROOFING COURSE – JULY – JANUARY 17 – 2024

I. Steel Works

  • 68 pieces of 12MM rods: GHS 4,764
  • 22 pieces of 3/8 rod: GHS 439.50
  • 2 coils of binding wire: GHS 160
  • Workmanship (steel bender): GHS 1,350
  • Total: GHS 6,713.50

II. Carpentry

  • 25 pieces of cyber board: GHS 2,125
  • 7 pieces of bush cut board: GHS 560
  • Boxes of 4 and 3 inches & wall nails: GHS 450
  • Workmanship (carpenter): GHS 2,200
  • Total: GHS 5,335

III. Masonry

  • 15 bags of 42.5R cement (beam casting and pillars): GHS 1,590
  • 38 bags of 32.5R cement (block laying): GHS 3,268
  • Lentil concrete casting: GHS 2,700
  • Block laying labour: GHS 5,480
  • Total: GHS 13,038

IV. Building Supplies

  • 1,400 pieces of 5 inches hollow blocks: GHS 10,620
  • 2 trips of sand: GHS 5,400
  • 1 trip of stones: GHS 2,800
  • Total: GHS 18,820

V. Miscellaneous and T&T

  • Miscellaneous costs: GHS 1,000
  • T&T cost: GHS 660
  • Total: GHS 1,660

Total Cost for Phase 2

  • GHS 45,791 

 

Adding Phase 1 + Phase 2 :

GROSS TOTAL : 72,816.5 GHS